All Systems Operational

Connectivity




Operational

Power




Operational

Environment




Operational

Other Systems and Services




Operational

Cloud Services




Operational

Infrastructure as a Service




Operational

External Services

MS Office365

Scheduled Maintenance

Schedule

November 11, 2024 07:00 - November 15, 2024 17:00 CET

Components

Environment

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies plc shall be scheduling preventive maintenance on the cooling units within MTH-R1, MTH-R2, and MTH-R3 as per the below schedule: Schedule: Start: 11/11/2024 - 07:00 CET End: 15/11/2024 - 17:00 CET We are not expecting these works to be service-affecting. However, during this period, brief temperature fluctuations might be experienced. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

November 13, 2024 06:00 - 15:00 CET

Components

Connectivity

Locations

DDoS Mitigation

Description

BMIT Technologies plc will be performing scheduled works on its DDoS Mitigation system, affecting the mentioned service as per the below schedule: Start: 13/11/2024 - 06:00 CET End: 13/11/2024 - 15:00 CET During this maintenance, the BMIT DDoS Mitigation Service will be temporarily unavailable. Active clients will be routed out of mitigation at the beginning of the maintenance and routed back into mitigation upon its completion DDoS Mitigation Service provided by our international carrier [Colt] will be available normally and will not be affected by this work. BMIT Technologies plc performs maintenance to continue to deliver optimal performance, reliability, and security. BMIT strives to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. BMIT hopes you understand that such maintenance is necessary to benefit you and your customers.

Schedule

November 13, 2024 08:30 - November 15, 2024 08:30 CET

Components

Infrastructure as a Service

Locations

Microsoft Azure Stack

Description

BMIT Technologies plc will be performing scheduled works on its Microsoft Azure Stack infrastructure as per the below schedule. Schedule: Start: 13/11/2024 - 08:30 CET End: 15/11/2024 - 08:30 CET The maintenance involves each Azure Stack infrastructure VM being placed in maintenance and restarted. After each restart, there might be some reconnection that experiences performance degradation. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

November 18, 2024 07:00 - November 22, 2024 16:00 CET

Components

Environment

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies plc together with its Supplier shall be performing scheduled preventive maintenance on the Fire Suppression System at MTH [Handaq] data centres as per schedule. Schedule: Day 1 Start: 18/11/2024 - 07:00 CET End: 18/11/2024 - 16:00 CET Day 2 Start: 19/11/2024 - 07:00 CET End: 19/11/2024 - 16:00 CET Day 3 Start: 20/11/2024 - 07:00 CET End: 20/11/2024 - 16:00 CET Day 4 Start: 21/11/2024 - 07:00 CET End: 21/11/2024 - 16:00 CET Day 5 Start: 22/11/2024 - 07:00 CET End: 22/11/2024 - 16:00 CET We are not expecting these works to be service-affecting. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the work being done during this maintenance window. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

November 18, 2024 07:00 - November 22, 2024 16:00 CET

Components

Environment

Locations

MTS-R1

Description

BMIT Technologies plc together with its Supplier shall be performing scheduled preventive maintenance on the Fire Suppression System at MTS data centre as per schedule. Schedule: Day 1 Start: 18/11/2024 - 07:00 CET End: 18/11/2024 - 16:00 CET Day 2 Start: 19/11/2024 - 07:00 CET End: 19/11/2024 - 16:00 CET Day 3 Start: 20/11/2024 - 07:00 CET End: 20/11/2024 - 16:00 CET Day 4 Start: 21/11/2024 - 07:00 CET End: 21/11/2024 - 16:00 CET Day 5 Start: 22/11/2024 - 07:00 CET End: 22/11/2024 - 16:00 CET We are not expecting these works to be service-affecting. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the work being done during this maintenance window. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

November 22, 2024 07:00 - 12:00 CET

Components

Environment

Locations

MTS-R1

Description

BMIT Technologies will be performing a preventive inspection on its Fire Suppression System at MTS generators fuel room area as per schedule. Start: 22/11/2024 - 07:00 CET End: 22/11/2024 - 12:00 CET BMIT Technologies is not expecting these works to be service-affecting. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.