Planned Maintenance In Progress

Description

BMIT Technologies plc together with its suppliers shall be performing structural works within MTH premises. These works are required to further increase the overall security and safety within our facility and will include the replacement/covering of certain apertures in MTH-R1 and MTH-R2, as per the below schedule. Schedule: Start: 28/09/2020 - 07:00 CEST End: 03/10/2020 - 19:00 CEST We are not expecting these works to be service affecting. However, during this period, brief temperature fluctuations might be experienced. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the works being done during this maintenance window. We remain at your service should you require further information. Please do not hesitate to contact us on support@bmit.com.mt We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact to our customers however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Components

Environment

Locations

MTH-R1, MTH-R2

Schedule

September 28, 2020 07:00 - October 3, 2020 19:00 CEST



September 28, 2020 07:00 CEST
[Update] Scheduled maintenance is starting.

Connectivity




Operational

Power




Operational

Environment




Planned Maintenance

Other Systems and Services




Operational

Cloud Services




Operational

Infrastructure as a Service




Operational

Scheduled Maintenance

Schedule

October 5, 2020 06:00 - 09:00 CEST

Components

Power

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies shall be performing MTH On-load generator testing as per the below schedule. Schedule: Start: 05/10/2020 - 06:00 CEST End: 05/10/2020 - 09:00 CEST BMIT Technologies shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

October 5, 2020 08:00 - 12:00 CEST

Components

Power

Locations

MTS-R1

Description

BMIT Technologies shall be performing MTS On-load generator testing as per the below schedule. Schedule: Start: 05/10/2020 - 08:00 CEST End: 05/10/2020 - 12:00 CEST BMIT Technologies shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

October 7, 2020 08:00 - October 8, 2020 17:00 CEST

Components

Environment

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies together with its Supplier shall be performing scheduled preventive maintenance on the Fire Suppression System at MTH data center as per schedule. Schedule: Start: 07/10/2020 - 08:00 CEST End: 08/10/2020 - 17:00 CEST We are not expecting these works to be service affecting. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the works being done during this maintenance window. We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

October 12, 2020 09:00 - October 13, 2020 16:00 CEST

Components

Power

Locations

MTS-R1

Description

As part of our continuous efforts to deliver the best service, BMIT Technologies in conjunction with its contracted power engineers will be performing the annual power infrastructure Thermography, covering installations of MTS-R1 as per the below schedule. Schedule: Day 1: 12-10-2020 Day 2: 13-10-2020 Time: 09:00 CEST to 16:00 CEST each day. Service is not expected to be interrupted and works will be carried out on a single feed at a time. We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers. We remain at your service should you require further information. Please do not hesitate to contact us on support@bmit.com.mt

Schedule

October 13, 2020 08:00 - October 15, 2020 17:00 CEST

Components

Infrastructure as a Service

Locations

Microsoft Azure Stack

Description

BMIT Technologies will be performing scheduled upgrades to its Microsoft Azure Stack as per the below schedule. Schedule: Start: 13/10/2020 - 08:00 CEST End: 15/10/2020 - 17:00 CEST We are not expecting these works to be service affecting. BMIT Technologies shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers' however, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.