All Systems Operational

Connectivity




Operational

Power




Operational

Environment




Operational

Other Systems and Services




Operational

Cloud Services




Operational

Infrastructure as a Service




Operational

External Services

MS Office365

Scheduled Maintenance

Schedule

December 1, 2025 06:00 - 09:00 CET

Components

Power

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies plc shall be performing MTH On-load generator testing as per the below schedule. Schedule: Start: 01/12/2025 - 06:00 CET End: 01/12/2025 - 09:00 CET BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 1, 2025 07:00 - December 2, 2025 16:00 CET

Components

Environment

Locations

MTH-R1, MTH-R2, MTH-R3

Description

BMIT Technologies plc, together with its Supplier, shall be performing scheduled preventive maintenance on the Fire Suppression System at MTH [Handaq] data centres as per schedule. Schedule: Start: 01/12/2025 - 07:00 CET End: 02/12/2025 - 16:00 CET We are not expecting these works to be service-affecting. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the work being done during this maintenance window. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 1, 2025 08:00 - 12:00 CET

Components

Power

Locations

MTS-R1

Description

BMIT Technologies plc shall be performing MTS On-load generator testing as per the schedule below. Schedule: Start: 01/12/2025 - 08:00 CET End: 01/12/2025 - 12:00 CET BMIT Technologies plc shall closely monitor progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 2, 2025 09:00 - 13:00 CET

Components

Cloud Services

Locations

Cloud Storage

Description

BMIT Technologies plc will be performing planned maintenance works on its Cloud Storage infrastructure as per the schedule below: Schedule: Start: 02/12/2025 - 09:00 CET End: 02/12/2025 - 13:00 CET BMIT Technologies plc is not expecting that such works will be service-disruptive. Our Support is available to provide up-to-date status information or additional details, should you have any questions during the maintenance. We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 3, 2025 07:00 - December 5, 2025 16:00 CET

Components

Environment

Locations

MTS-R1

Description

BMIT Technologies plc, together with its Supplier, shall be performing scheduled preventive maintenance on the Fire Suppression System at MTS data centre as per schedule. Schedule: Start: 03/12/2025 - 07:00 CET End: 05/12/2025 - 16:00 CET We are not expecting these works to be service-affecting. For health and safety reasons, access to the data room will be controlled and we may also restrict access depending on the work being done during this maintenance window. We perform maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 3, 2025 07:30 - 16:00 CET

Components

Environment

Locations

MTS-R1

Description

BMIT Technologies plc shall be performing emergency maintenance on one of the cooling units in MTS-R1 as per the below. Schedule: Start: 03/12/2025 - 07:30 CET End: 03/12/2025 - 16:00 CET We are not expecting these works to be service-affecting. However, during this period, brief temperature fluctuations might be experienced. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 3, 2025 08:30 - 16:30 CET

Components

Cloud Services

Locations

Cloud Control Panel

Description

BMIT Technologies plc shall be performing scheduled maintenance on its Cloud Control Panel as per the below schedule. Schedule: Start: 03/12/2025 - 08:30 CET End: 03/12/2025 - 16:30 CET BMIT Technologies plc is not expecting these works to be service-affecting. However, during this maintenance window, the control panel may experience intermittent periods of unavailability. Customers using the control panel may also experience delays in billing, provisioning, and management of subscriptions. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 4, 2025 07:00 - 17:00 CET

Components

Power

Locations

MTS-R1

Description

BMIT Technologies will be performing off-load generator maintenance on Generator B at Smart City [MTS] as per the schedule below. Schedule: Start: 04/12/2025 - 07:00 CET End: 04/12/2025 - 17:00 CET We are not expecting these works to be service-affecting. However, during this period infrastructure will be running with reduced resilience. We perform maintenance to continue to deliver optimal performance, reliability, and, security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 9, 2025 07:00 - December 11, 2025 17:00 CET

Components

Environment

Locations

MTH-R3

Description

BMIT Technologies plc shall be performing scheduled maintenance on one of the cooling systems in MTH-R3 as per the schedule below: Schedule: Start: 09/12/2025 - 07:00 CET End: 11/12/2025 - 17:00 CET We are not expecting these works to be service-affecting. However, during this period, brief temperature fluctuations might be experienced. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 9, 2025 09:00 - 13:00 CET

Components

Cloud Services

Locations

Cloud Storage

Description

BMIT Technologies plc will be performing planned maintenance works on its Cloud Storage infrastructure as per the schedule below: Schedule: Start: 09/12/2025 - 09:00 CET End: 09/12/2025 - 13:00 CET BMIT Technologies plc is not expecting that such works will be service-disruptive. Our Support is available to provide up-to-date status information or additional details, should you have any questions during the maintenance. We perform maintenance to continue to deliver optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.

Schedule

December 10, 2025 08:30 - December 12, 2025 08:30 CET

Components

Infrastructure as a Service

Locations

Microsoft Azure Stack

Description

BMIT Technologies plc will be performing scheduled work on its Microsoft Azure Stack infrastructure as per the schedule below. Schedule: Start: 10/12/2025 - 08:30 CET End: 12/12/2025 - 08:30 CET The maintenance involves each Azure Stack infrastructure VM being placed in maintenance and restarted. After each restart, there might be some reconnection that experiences performance degradation. BMIT Technologies plc shall be closely monitoring progress during this maintenance and will keep you informed of development or prior to taking any required action. BMIT Technologies plc performs maintenance to continue delivering optimal performance, reliability, and security. We strive to perform them without impact on our customers. However, the possibility always exists that a maintenance event can have unintended consequences up to and including unplanned or extended service interruption. We hope you understand that such maintenance is necessary to benefit you and your customers.